Current Progress
Project Summary
Following are project and chapter summaries. Chapter-specific logs
are available through the links on the left. Check my write-up on
Building Time Defined to see how I am
recording my time.
|
Project Start Date |
May 29, 2004 |
|
Last Work Date |
November 20, 2006 |
|
Estimated Hours to Complete |
3,500 |
|
Total Hours Worked |
288.8 |
|
Remaining Hours to Complete |
3,211 |
|
Approximate % Complete |
8% |
|
Days Elapsed |
906 |
|
Years Elapsed |
2.5 |
|
Pace since Project Start: |
|
|
Average Hours Worked/Day |
0.32 |
|
Estimated Completion Date |
June 22, 2034 |
|
Pace in Last 12 Months (since 11/26/2005) |
|
Average Hours Worked/Day |
0.53 |
|
Estimated Completion Date |
August 12, 2023 |
|
Pace in Last 3 Months (since 8/23/2006) |
|
Average Hours Worked/Day |
0.53 |
|
Estimated Completion Date |
May 17, 2023 |
|
Pace in Last 1 Month (since 10/22/2006) |
|
Average Hours Worked/Day |
0.63 |
|
Estimated Completion Date |
October 8, 2020 |
Chapter Summary
|
|
|
|
Time |
|
Chapter |
Name |
Progress |
Budget |
Actual |
|
1 |
Introduction |
100% |
16.0 |
16.0 |
|
2 |
Bill of Materials |
100% |
4.0 |
4.0 |
|
3 |
Education |
100% |
12.0 |
12.0 |
|
4 |
Fuselage Bulkheads |
95% |
142.0 |
135.0 |
|
5 |
Fuselage Sides |
95% |
120.0 |
113.8 |
|
6 |
Fuselage Assembly |
32% |
125.0 |
39.5 |
|
7 |
Fuselage Exterior |
0% |
100.0 |
0.0 |
|
8 |
Headrest & Seat Belts |
0% |
100.0 |
0.0 |
|
9 |
Main Gear & Landing Brake |
0% |
100.0 |
0.0 |
|
10 |
Canard |
0% |
100.0 |
0.0 |
|
11 |
Elevators |
0% |
100.0 |
0.0 |
|
12 |
Canard Installation |
0% |
8.0 |
0.0 |
|
13 |
Nose, Nose Gear, & Brakes |
0% |
100.0 |
0.0 |
|
14 |
Center Section Spar |
0% |
100.0 |
0.0 |
|
15 |
Firewall |
0% |
100.0 |
0.0 |
|
16 |
Control System |
0% |
100.0 |
0.0 |
|
17 |
Trim System |
0% |
100.0 |
0.0 |
|
18 |
Canopy & Turtleback |
0% |
100.0 |
0.0 |
|
19 |
Wings, Ailerons, & Wing Attach |
0% |
100.0 |
0.0 |
|
20 |
Winglets & Rudders |
0% |
100.0 |
0.0 |
|
21 |
Strakes, Fuel, & Baggage |
1% |
100.0 |
0.5 |
|
22 |
Electrical |
0% |
250.0 |
0.0 |
|
23 |
Engine Installation |
0% |
250.0 |
0.0 |
|
24 |
Covers & Fairings |
0% |
150.0 |
0.0 |
|
25 |
Finishing |
0% |
150.0 |
0.0 |
|
26 |
Upholstery |
0% |
150.0 |
0.0 |
|
27 |
Reserved Time |
N/A |
755.0 |
N/A |
|
|
Totals |
8% |
3500.0 |
288.8 |
|